Failure to File

1.  Second notice - 30 days past the due date, the Commission sends the operator a second notice of the need to file Form H-10.

2.  Continued delinquency - Enforcement action is initiated 30 days after the second notice if the operator has not contacted Technical Permitting regarding compliance.
  • The well is sealed if no production exists on lease.
  • The lease pipeline connection is severed if production exists. 

    NOTE: Always respond to Commission requests to avoid unnecessary enforcement action. The Commission will work with an operator who is making a diligent effort to comply.

Last Updated: 3/24/2016 10:02:21 AM